Morgan Sindall/BAM smart motorway double confirmed

Date: 09 Jan 2018

Morgan Sindall and BAM Nuttall joint venture has confirmed the value of two contracts at £322m to deliver part of Highways England’s smart motorway programme.

The first contract, a two-stage design and build contract worth £104m, is to upgrade 10 miles of the M62 between Warrington (J10) and Manchester (J12).

BMJV, supported by design partners WSP and AECOM, started design work last month, with works planned to start on site from spring 2018.

It second contract, worth £218m, will see the M27 between junctions 4 and 11 converted to create permanent dual 4-lane all lane running along the 15-mile stretch.

Consultants SWECO/Mott Macdonald and WSP have just started the design work with construction now due to begin in the spring.

Paul Gott, managing director of Highways at Morgan Sindall, said: “These contracts mark the start of two more prestigious projects for BMJV.

“The established relationship between our two companies enables us to provide the best possible service to enhance the capacity and reliability of the UK’s strategic road network in order to improve journeys for road users.”

[Credit: constructionenquirer.com]

BACK
  • SHARE
Image 1 Blog
A Guide to Finding Quantity Surveyor Jobs in London
21 Jul 2023
TOP 10 SKILLS 1 Blog
Top 10 Skills That Construction Recruiters Look for in Candidates in 2023
24 May 2023
Site Engineer Job Interview Blog
Site Engineer Jobs: 7 Ways to Make an Impression During the Interview
28 Apr 2023